Redistribution of costs for air conditioning at the Regional Archive and Public Library of Madeira
The Regional Government has adjusted the payment plan for the air conditioning project at the Regional Archive and Public Library of Madeira, with a total investment exceeding 1.1 million euros.
Through Ordinance no. 256/2026, the Regional Secretariat for Equipment and Infrastructure has proceeded with the amendment and redistribution of budgetary charges related to the procedure for "REGIONAL ARCHIVE AND PUBLIC LIBRARY OF MADEIRA - AIR CONDITIONING" (process no. 6/2026).
The total value of the contract remains at €1,129,383.03, with the payment plan staggered as follows:
- Fiscal year 2026: €547,123.08
- Fiscal year 2027: €582,259.95
VAT at the current legal rate is added to the indicated values. This measure allows for the continuation of the project to improve the conservation conditions and thermal comfort of the cultural infrastructure, with the funds for 2027 to be included in the respective regional budget proposal.
Related articles
Government Declares Public Utility for Roundabout on ER 120 in Vila Baleira
The Government Council authorized the expropriation of land in Porto Santo for the construction of a roundabout on Regional Road 120, aiming to increase road safety.
Regional Government Authorizes Contract Amendment for Quebradas/Amparo Link
The Regional Government has authorized a specific change to the addendum of the construction contract for the tunnels of the new road link.
Government authorizes 10 million euros for new Quebradas/Amparo road link
Ordinance No. 521/2026 authorizes the distribution of 10.02 million euros for the second phase of the new road link between Quebradas and Amparo.