Ordinance redistributes budgetary burdens for the requalification of inpatient units in the Autonomous Region of Madeira.
Through Ordinance no. 203/2026, the Regional Secretariat for Health and Civil Protection has amended and redistributed the budgetary burdens allocated to the execution of investment C01-i05-RAM - Strengthening the Regional Health Service of the Autonomous Region of Madeira.
The sub-investment, focused on the Expansion, Development and Improvement of the Integrated Continuing Care Network, has a total amount of €4,336,407.73, financed by the Recovery and Resilience Plan (PRR). The main objective is the requalification of existing places in the NETWORK's inpatient units, specifically in the typology of Long-Term and Maintenance Integrated Continuing Care.
The distribution of financial burdens was defined as follows:
The burdens for 2026 are covered by the budget of the Institute of Health Administration, IP-RAM.
The Region has authorised the allocation of costs for a cleaning contract covering several SESARAM facilities. The base price is €949,066.80, plus VAT at 22%, with the expenditure planned for 2027.
The renewed contract with CPE - Companhia de Parques de Estacionamento, S.A. secures the premises used by Dr. Nélio Mendonça Hospital’s Outpatient Clinic for a further five years. The total cost is €381,471.48, exempt from VAT.
Adaptations are being considered at the Porto da Cruz Nursing Home and São Roque Community Centre to accommodate people who are medically fit for discharge but cannot return home for social reasons. The number of places has not yet been set, and the works have not been authorised.