The Region has redistributed the costs of the procedure to rebuild coastal protection at the Seixal wastewater treatment plant over three years. The total is €2.96 million, plus VAT.
Ordinance No. 573/2026 redistributes the budget costs of the procedure “SEIXAL WASTEWATER TREATMENT PLANT - RECONSTRUCTION OF COASTAL PROTECTION”, file No. 1/2026. The total remains €2,960,000, plus VAT at the applicable legal rate.
The costs are divided as follows:
The ordinance redistributes the amounts set out in Ordinance No. 356/2026, published on 23 July. Any balance identified for a given year may be added to the amount allocated for the following year. The 2026 expenditure is covered by the Budget of the Autonomous Region of Madeira, while the funds for 2027 and 2028 will be included in the respective budget proposals.
Signed on 28 September, Ordinance No. 573/2026 enters into force on the first working day following its publication.
The Regional Secretariat for Equipment and Infrastructure opens a competition for the post of Head of River Hydraulics Division, with applications accepted for 7 working days.
Portaria No. 633/2026 redistributes the EUR 1,387,000.03 cost of rebuilding hydraulic infrastructure on the Ponta Delgada Stream across 2026, 2027 and 2028.
Portaria n.º 631/2026 authorises the distribution of 905,000.00 € for consolidating the cliff at the Ribeira Brava quay, all to be paid in 2027.