Ordinance No. 356/2026 amends the budgetary phasing for the reconstruction work of the maritime protection of the Seixal Wastewater Treatment Plant.
An amendment to the financial distribution for the reconstruction of the maritime protection of the Seixal Wastewater Treatment Plant (WWTP) has been approved. The legal instrument, Ordinance No. 356/2026, modifies Ordinance No. 34/2026 which had initially planned the investment.
The total value of the procedure remains at €2,960,000.00 (two million, nine hundred and sixty thousand euros). However, the new ordinance redistributes this amount across the financial years 2026 and 2027 as follows:
As with other legal instruments, it is established that the amount set for each year may be increased by the balance carried over from the previous year. The mentioned values will also be increased by VAT at the applicable legal rate.
The expenditure for the year 2026 has specific budgetary coverage in the RAM Budget for 2026. The necessary funds for 2027 will be included in the budget proposal for that year. The ordinance came into force on the working day following its publication.
The Region has approved the multi-year allocation of costs for the design and construction of the Machico Pavilion. The total amount is €4,175,000, plus VAT, with the largest share scheduled for 2029.
The Regional Government has authorised additional construction supervision and monitoring services for Madeira Central Hospital, at an extra cost of up to €29,620. The service period increases from 105 to 107 months, and the contract’s maximum term rises from 228 to 230 months.
Regional funding for the rehabilitation of the Praia Formosa Seafront remains capped at €4,828,876.35, but the costs have been rescheduled through 2029. The change follows the lack of valid bids for the second phase of the works and a revision of the project.