Regional Government and São Vicente Municipality Amend Contract for Infrastructure Recovery
The Autonomous Region of Madeira and the Municipality of São Vicente have amended the programme contract for the recovery of infrastructure damaged by the 2020 storm, extending its validity and adjusting the funding.
The sixth amendment to the technical and financial cooperation programme contract between the Autonomous Region of Madeira and the Municipality of São Vicente has been published. The agreement, initially signed in May 2021, aims at the recovery and reconstruction works of municipal infrastructure affected by the storm of 25 December 2020.
Contract No. 137/2026, signed by the Regional Secretary for Finance, Duarte Nuno Nunes de Freitas, and the President of the Municipality of São Vicente, José Carlos Gonçalves, introduces the following main changes:
- Extension of the validity period: The programme contract now ends on 31 December 2026.
- Funding adjustment: The maximum financial contribution from the Region for the works remains at 2,299,914.30 euros. The annex to the contract details the distribution of this amount by year, from 2021 to 2026, with the allocation for 2026 being 64,344.67 euros.
- Budget classification: The regional funds are allocated under the budget heading 47.50.02.01.D.08.05.03 B0.SN - Support to Municipalities for 2020 Storms.
This amendment aims to ensure the completion of the reconstruction works in the municipality of São Vicente.
Related articles
Region Expropriates Land Plot for Funchal/Airport Expressway for 45,370.82 euros
The Regional Government has authorised the expropriation of a plot for the 2nd phase of the Funchal/Airport Expressway for 45,370.82 euros, according to Resolution No. 1063/2026.
IHM: 125.25 million in funding for expansion of public housing stock
Government reschedules payments to IHM, boosting 2026 and reducing 2030, while keeping the ceiling of 125,250,000.00 € for housing expansion through 2030.
Additional supervision expenses for Hospital Central da Madeira corrected to €23,988.00
Resolution No. 1072/2026 corrects the ceiling on additional supervision expenses for the construction of the Hospital Central da Madeira to €23,988.00.